Tottenham Track Slew

This project was embarked on to separate regional and metropolitan train services and make room for the future construction of a 40km twin track rail link from Southern Cross Station to West Werribee. The works were completed in a 7 week programme with a 2 week shutdown.

DRASOL were engaged during the time-critical shutdown period to provide round the clock crews installing cross track services, signalling pit and pipe infrastructure and track formation drainage.

Services included:

• Mobilisation of plant and personnel from Adelaide
• Signalling pit and pipe infrastructure
• Under track crossings
• Track drainage

CLIENTColeman Rail
LOCATIONTottenham, Victoria
SERVICESUnder track crossings, signalling infrastructure, track drainage
TIMELINE2011