SA Water’s Morgan-Whyalla Pump Station 3 is the third out of a total of four pumping stations on the Morgan to Whyalla pipeline that delivers approximately 66,000 megalitres of valuable water annually to the Upper Spencer Gulf towns in South Australia.
Working closely with our clients Next Generation Electrical, our work teams successfully completed the installation of 19,656 PV modules mounted on 234 individual trackers across the 19 hectare site.
The final commissioning of this site will further reduce the asset owner’s reliance on imported electricity to power the pumping station and various other assets.
CLIENT | Next Generation Electrical |
LOCATION | Geranium Plains, South Australia |
SERVICES | Mechanical and PV Module Installation, Quality Assurance, Technical Support, Tooling and Materials Handling. |
SYSTEM | NEXTracker – 234 Trackers installed and 19,656 Modules |
TIMELINE | 2019 |
CAPACITY | 7.5 MW |